 GMT - Construction of the Engineered Barrier System
 
 GMT Project
 GMT Introduction
 Experimental Concept
 Laboratory Programme »
 Silo Excavation
 Site Characterisation
 Construction of the EBS
 Field Testing »
 Excavation of the EBS »
 Subtask Modelling
 Initial Conclusions
  < Home Page
Home > GMT Project
Gas Migration in EBS and Geosphere (GMT)
Construction of the Engineered Barrier System

Construction steps

Emplacement of Bentonite/Sand material

Construction of concrete silo


Concrete silo base

Concrete silo re-inforcement

Emplacement in the annulus

Top concrete silo forms

Top concrete silo instrumentation overview

Instrumentation

In all some 210 instruments have been placed within the EBS and backfill including 96 piezometers (internal and external), 10 temperature sensors, 11 total pressure cells and 70 Time Domain Reflectometers (TDRs) to measure water content (and hence saturation) of the EBS. Also included are gas samplers and novel fibre optic measuring systems.


Side Elevation showing Instrumentation

Level 8 (Concrete silo and sand/bentonite)

       <img src="images/instruments.gif" width=280 height=210 border=0>


Horizontal TDR

Pressure and humidity sensors

Instrumentation of Level 2

Instrumentation as built

Instrumentation of top Level

 

 
Gas Migration in EBS and Geosphere (GMT) Experiment  