Final configuration of profile boreholes. Approximately 24
hours before blasting every second profile borehole was filled
with Bristar (chemical expansion agent with water) in order
to pre-stress the rock mass. The explosive loading in the
remaining boreholes could thus be reduced.
During this final excavation the rock fractured along the
profile boreholes giving a surface roughness of less than
10 cm.
|