The aims of the excavation and characterisation phase of the Gas
Migration Test (GMT) were:
The excavation and characterisation of the silo was carried out
in a series of eight steps (explained in greater detail in the sections
shown in the side menu above):
Step 1: Depressurisation of GMT Cavern.
Step 2: Cutting through the concrete plug.
Step 3: Removal of backfill from GMT Cavern.
Step 4: Investigations from top of Layer 12.
Step 5: Removal of sand/bentonite by layers to top
of concrete silo.
Step 6: Investigations in Layers 8 and 7.
Step 7: Removal of Layers 6-5.
Step 8: Restoration of GMT site.