Grimsel Test Site (GTS)
Underground Research & Development URL
 
Home
Phase VI Experiments
CFM
LTD
T-H
NF-Pro
LCS
PSG
MTF
Phase V Experiments
CRR
EFP
FOM
FEBEX
GAM
GMT
HPF
 GMT - Excavation of the EBS - Removal of Layers 6-5
 
 » Excavation of the EBS
 Overview
 Depressurisation of Cavern
 Cutting of Concrete Plug
 Removal of Backfill
 Investigations of Layer 12
 Removal of Sand/Bentonite
 Investigations of Layers 8 & 7
 Removal of Layers 6 & 5
 Restoration of GMT site
  < Back to GMT Page
Home > GMT Project > Excavation of the EBS
Gas Migration in EBS and Geosphere (GMT)
Excavation of the EBS - Removal of Layers 6-5

Layer 6 and layer 5 were the bottom layers of the silo to be excavated.

Due to space limitations the excavation of the sand/bentonite was more difficult in the lower areas and excavation techniques had to be adapted to take account of the reduced space.

 

 


Core sampling from the bottom layers. In photo: GTS site manager Toni Bär

 

 
Gas Migration in EBS and Geosphere (GMT) Experiment  