Home
> HPF Project
> The Final Tracer Test
|
Hyperalkaline Plume in
Fractured Rock (HPF)
Final Tracer Test - Tracer Injection |
|
The tracer injection began on the 20th January with the circulation
of the 0.5 litre of cocktail in the equipment sorption stage.
Circulation of 0.5 litres of tracer
injection cocktail during the equipment sorption stage
|
Radiation Protection staff monitor
the injection area during the circulation of the 0.5 litre
equipment sorption cocktail.
|
However, extreme weather in the area forced the postponement of
the next stages for one week until conditions improved. Even leaving
Guttannen was difficult!
After postponing the injection, the
cars had to be dug from the car park in Guttannen.
|
This was easier said than done.
|
The following week the injections re-started. Firstly, the 5 litre
spike input stage was successfully carried out.

GTS manager Toni Bär prepares to dance
with joy as the Final Injection continues the following week.
Then the first 30 litre tank was connected and the top hat input
stage began.
The team from PSI (Max Rüthi
and Marc Grämiger) examine the data from the on-line
gamma spectrometers which monitor the inflow and outflow of
radionuclides
|
The tank is placed in a large watertight
tray and shielded with thick plexiglass. The mass of injected
tracer is monitored by the balance connected to the Data Acquisition
System
|
Leaving Handeck after the successful
injection
|
| |
|

The Final Tracer Test continues. On
17th February the field crew successfully replaced the tracer
solution with another 30 litres. The weather was much improved
from the previous visits. |

There is still a considerable depth
of snow at the entrance to the KWO tunnels. |
| |
|

The radioactive tracers are injected
from a large tracer tank coated with Teflon to minimise sorption
of the tracers onto the tank. The lighter material on the inside
wall of the tank is a result of condensation.
|

Urs Mäder (Uni. Bern) and Karam
Kontar (Solexperts) prepare the second 30 litre injection tank.
The long input of safety relevant tracers will continued for
another 4 weeks. |
|