Excavation of the HotBENT Cavern (Mar - Apr 2020)
Excavation of the HotBENT Cavern (Mar - Apr 2020)
HotBENT Cavern and DAS (data aquisition system) cabinet installation (Sep 2020)
End of gallery with cement liner section and instrumented Section S2 (spider) and fibre optics (red cables on
concrete) (Oct 2020)
Transport of heater module towards experimental section (Oct 2020)
Heater #1 instrumented and partially backfilled with GBM (Nov 2020)
Auger backfilling machine over heater #2 (Dec 2020)
Backfilling of last part of Sector 1 (with augers, lower front part: retaining wall of Plug 1) (Dec 2020)
Completed retaining wall of Plug 1 (Dec 2020)
Shotcreting of Plug 1 (Feb 2021)